NATIONAL CIRCUIT
Brief
Design and install a large area work & containment bridging platform over the atrium void, to provide access for glass roof installation. Design and install a travelling large area work and containment platform, suspended from the bridging scaffold, to travel from level to level, to facilitate installation of slab edge cladding and balustrades while enabling groundworks to proceed simultaneously.
Features
- Bridging Platform Area – 9m x 20m
- Travelling Platform Area -7.5m x 18m
- Vertical Travel – 30m
- Traveling Platform powered by two pairs of 240V, 20A electric scaffold hoists
- Independent overspeed safety brakes operate in tandem with hoists.
Share
Project Name
National Circuit
Principal
Lend Lease
Installation
Over-Void 'SKYDECK' Platform With Travelling Void IN-FILL Platform
Related items
Hawkesbury Rail Bridge – Containment – Work Decks
BRIEF: Design and install catch / work platforms below the up and down rail lines,…
BRIDGEPOINT, SPIT JUNCTION
Brief Design & Install a suspended scaffold installation to the underside of the pedestrian bridge…
Westmead Hospital – Core cladding repair – Winch driven scaffold
BRIEF: Above were asked by their client to provide an efficient solution to replace cladding…
PORT BOTANY REDEVELOPMENT PROJECT
Brief Design and install a stretcher stairs and walkway bridge to provide access over the…