PORT BOTANY REDEVELOPMENT PROJECT
Brief
Design and install a stretcher stairs and walkway bridge to provide access over the rail corridor between the work site and the site compound. The design to ensure the installation does not encroach into the rail corridor. The installation methodology to minimise track possession duration.
Features
- 14.5m clear span bridge suspended between stretcher stair tower abutments.
- Bridge pre-assembled then craned into position and connected to stair towers.
- 1.4m wide bridge and stairways.
- Stair towers anchored to concrete barriers for stability and wind resistance.
- 2.5kPa load rating.
Share
Project Name
Port Botany Redevelopment Project
Principal
Fulton Hogan
Installation
Access Bridge With Stairs
Categories
Related items
Built Core – 4 & 6-8 Parramatta Square – Link Bridge Installation Scaffold
BRIEF: Design and install containment and work perimeter scaffold spanning from one building to adjacent…
SYDNEY CRICKET GROUND UPGRADE
Brief Design and Install BCC compliant stairway installation to provide temporary public stair access between…
SALT PAN CREEK RAILWAY BRIDGE TRUSS REPLACEMENT
Brief Design & Install a suspended scaffold installation to the underside of the railway bridge…
WIN STADIUM, WOLLONGONG
Brief Design and install a propping tower installation to support the 100 Tonne stadium roof…