BARANGAROO TOWER 1
Brief
Design and install a falsework solution to allow pouring of crane penetration infills at 3 levels, simultaneously. All penetrations directly above each other. Falsework needed to span over the penetration below, while allowing formwork installation to pour the slab above.
Features
- Falsework structures were built away from edge of penetration and rolled into position
- Access was maintained to pour the L03, L02 and L01 infills without obstruction due to falsework spanning over the voids
- U head jacks and internal ladder access allowed traditional formwork to be insalled quickly and safely
Share
Project Name
BARANGAROO TOWER 1
Principal
Lend Lease
Installation
FalseworkK Scaffolds
Related items
Shape Star Casino
BRIEF: Design & Install Scaffolding and Swinging Stages for recladding FEATURES: 50t Birdcage within Lobby…
SYDNEY HARBOUR BRIDGE REFURBISHMENT
Brief Design and install a suspended scaffold installation to the underside of the Sydney Harbour…
CENTRAL PARK
Brief Design and install modular special duty swinging stages to facilitate installation and planting of…
NORTHCONNEX – DARLING MILLS BRIDGE WIDENING
Brief Design & install various stretcher stair installations to provide safe access to the abutments…