BARANGAROO TOWER 1
Brief
Design and install a falsework solution to allow pouring of crane penetration infills at 3 levels, simultaneously. All penetrations directly above each other. Falsework needed to span over the penetration below, while allowing formwork installation to pour the slab above.
Features
- Falsework structures were built away from edge of penetration and rolled into position
- Access was maintained to pour the L03, L02 and L01 infills without obstruction due to falsework spanning over the voids
- U head jacks and internal ladder access allowed traditional formwork to be insalled quickly and safely
Share
Project Name
BARANGAROO TOWER 1
Principal
Lend Lease
Installation
FalseworkK Scaffolds
Related items
Macquarie University Hospital – Swinging Stages- Clading Replacement
BRIEF: Swinging Stagesfor Cladding replacement FEATURES: Swinging Stages projecting through plant room rooves x 9…
LAWRENCE HARGRAVE DRIVE
Brief Design and install an access and containment scaffold suspended from the LHD footpath to…
Westmead Hospital – Core cladding repair – Winch driven scaffold
BRIEF: Above were asked by their client to provide an efficient solution to replace cladding…
NATIONAL CIRCUIT
Brief Design and install a large area work & containment bridging platform over the atrium…